Case completed construction of the tunnel nearby to downtown Indianapolis, so crews worked successfully within extremely small footprints.

The project

In order to improve the water quality for the City of Indianapolis, a combined sewer overflow (CSO) collection system was planned. The first phase of the project was the Indianapolis Deep Rock Tunnel Connector. From October 2012 to June 2013, Case Foundation installed drop, vent, and utility shafts at six unique site locations.

The challenge

The shafts that were required on this large operation were installed in extremely small footprints due to the location of the tunnel near downtown Indianapolis.

The solution

Once the shafts were excavated to the top of rock, a piece of full length, permanent steel casing was twisted into the top of rock for a seal within 0.5% verticality, the annular space was then filled with grout by tremie methods. Case Foundation installed a total of three drop shafts, three vent shafts and three utility shafts ranging 8 feet to 14.5 feet in diameter and 120 feet of overburden excavation under bentonite slurry support.

Project Facts

Owner

Citizens Energy Group

Main Contractor(s)

J.F. Shea / Kiewit, JV

Keller Business Unit(s)

Case Foundation

Engineer

N/A